The outside of the 40,000+ square foot warehouse addition is looking closer to completion, at least on the outside. The roof is on and they are finishing the trim work around the top.
Consumers Energy was out this week to install a second transformer for the addition. The addition is separated from the current warehouse by a concrete firewall and will have 4 large fire shutter doors that will separate the two parts of the building if there were a fire.
Next week they will begin laying the ground work before pouring the concrete floor. Electricians will be out to run conduit that will run under the floor and prep work will begin on the ground.